|
CHAPTER XIII
INITIAL RECORDS
|
1301
|
Initial Records of the Engineering Department
|
|
1302
|
Muster Sheets
|
|
1303
|
Register of Wages
|
|
1304
|
Muster Roll and Labour Pay
Sheet
|
|
1310
|
Unpaid Wages
|
|
1313
|
Payment to Suppliers and Contractors Record of Measurements
|
|
1315
|
Recording of Measurements
|
|
1322
|
Instructions for
maintenance of Measurement Books
|
|
1327
|
Standard Measurements
|
|
1328
|
Measurements based on Standard Type Drawings
|
|
1330
|
Measurements for
lump-sum Contract
|
|
1331
|
Approximate Measurements
|
|
1332
|
Measurements of
Ballast Train Work
|
|
1333
|
The measurement of ballast
|
|
1336
|
Petty Contract
Bill
|
|
1337
|
The Running on Account Bill
|
|
1338
|
The Final Bill
|
|
1339
|
The Hand
Receipt
|
|
1340
|
Preparation of Contractor's Bills
|
|
1342
|
Other Miscellaneous
Payments
|
|
1343
|
Bills for Stores Purchased
|
|
1344
|
Pay Order
|
|
1345
|
General
Rules
|
|
1354.
|
Check of Initial Record
|
1301. Initial Records on the Engineering Department relate to the payment of the following :
-
(i) Wages of labourers and members of work charged establishment.
-
(ii) Payments to contractors and others for work done, services rendered and materials
supplied.
-
(iii) Pay and allowances of Construction staff and other miscellaneous payments.
The method of preparation of initial records in all these cases is described in the following paragraphs.
1302. Muster Sheets.--The wages of labourers and work charged establishment are
charged through the muster sheets on which their daily attendance and absences are marked. Since some of
the labour employed may be those governed by the Minimum Wages Act, 1948, the Muster Roll form
prescribed under this Act has to be followed if separate Muster Rolls are adopted. The prescribed form is available
as Form No. 91 in Appendix 9 of Indian Railways Establishment Manual.
1303. Register of Wages.--Where separate Muster Rolls are used, since some of the
labour employed may be governed by the Minimum Wage Act 1948, a Register of Wages as prescribed [Form
E 1303] under this Act has to adopted. Alternately the combined Muster Roll and Labour Pay sheet
indicated in para 1304 may be adopted as pay sheet or register of wages.
Form E.1303 (Continued to........ List of forms)
1304. Muster Roll and Labour Pay Sheet.-- A combined Muster Roll and
Labour Pay Sheet can also be adopted. For this purpose the following form may be
used.
Form E.1304 (Continued to........ List of
forms)
1305.
One muster sheet should be maintained for each gang of labourers or a convenient group
of work-charged establishment. Before the commencement of a wage month, the Assistant Engineer
should issue the requisite number of blank muster sheet forms to each supervisor for the purpose of recording
the daily attendance of the labour working under him. Each muster sheet form so issued should bear the
initial of an officer not below the rank of Assistant Engineer on the top right corner as a token of its authenticity.
The muster sheet should be written up daily by the person deputed for the purpose, generally the
subordinate under whom the labour or the work charged staff concerned is employed.
1306.
The daily attendances and absences of labourers should be recorded in the muster
sheets in such a way as---
-
(i) To facilitate the correct calculation of the net wages of each person for the period of payment.
-
(ii) To render it difficult to tamper with or make unauthorised additions to or alterations in,
entries once made; and
-
(iii) To facilitate the correct classification of the cost of labour by works and sub-heads of
works where necessary.
The subordinate maintaining a muster sheet should, therefore, note in words the total number
of persons present on each day and give brief remarks as to the work or work on which the labour
was employed each day at the bottom of the sheet.
Assistant Engineers should check muster sheets as frequently as possible and record on the
spot the number of men present in words and in ink, over their initials.
1307. At the end of every wage month the muster sheets should be closed, the amount of
gross wages due to each labourer or work-charged employee should be worked out and the totals struck.
The muster sheets so completed should be collected by the supervisor and submitted through the
Assistant Engineer to the Executive Engineer with an abstract of all muster sheets submitted for checks and payment.
In the office of the Executive Engineer the muster sheets should be checked under the supervision of
the Divisional Accountant before they are sent to the Accounts Officer for arranging payment.
1308. Payments of muster sheets should be made and witnessed by the officer of the
highest standing available on the spot. The witnessing officer should certify to the payments individually or
by group, a the same time, specifying both in words and in figures, at the foot of the muster sheet, the
total amount paid on each date. Assistant Engineers should witness payments of all labour under one or
more subordinates each month. This should be done without warning.
1309.
Unpaid amounts, should, in the case of a muster sheet for men employed on several
works, be considered as relating to the most costly work in the group and subsequent payments of unpaid
amounts should be debited to that work, if the accounts of the work are still open, otherwise to the same head of
the capital account.
1310. Unpaid Wages.-Unpaid amounts on muster sheets will be paid on Extract Muster
Sheets/Pay Orders. In all such cases a counter reference should be made by the executive officer against
the corresponding entry in the Unpaid Wages list form A.1954 supplied by the Cashier. This precaution
is necessary to avoid more than one payment. Unpaid amounts on muster sheets will not be posted in
the Register of Works or Accounts.
1311.
Muster sheets should never be prepared in duplicate. They should not ordinarily pass
beyond the office of the responsible disburser. The Accounts Officer may, however, send for the paid
muster sheets in connection with any accounts discrepancy or any investigation.
1312. The payment of daily labour through a contractor instead of through muster sheets
and labour pay sheets in the usual way is objectionable in principle. In a case of great emergency it
may sometimes be found impossible to employ labour otherwise than through a contractor. Should it be
possible in such cases to determine the quantities of work done after its completion or at intervals during its
progress the payment to the contractor should be on the basis of work actually
excecuted. But if, as in the case
of urgent repair of breaches of lines this method of payment is not practicable, it is permissible to pay
the contractor on the basis of number of labourers employed day by day, his own profit or commission
being included in the rates allowed. When this course is adopted, a report of the number of labourers of
each class employed, day by day should be made in the following form (Form E. 1312) by the
subordinate incharge of the work daily to the Assistant Engineer to enable the latter to keep a check on the
expenditure and to deal with the contractor's claim when received. To avoid disputes the contractor should be
asked to sign the Daily Report of Labour (sent by the subordinates) in token of their acceptance. The use
of muster sheets or the measurement book is not permissible in such cases.
Form No. 1312
S. No................................. ..........................................RAILWAY
ENGINEERING DEPARTMENT
Division............................. Office........................
DAILY REPORT OF LABOUR EMPLOYED ON.............................SECTION
Sub-Division.................................................Division...........................................
Name of work......................................................................................................
Daily report for.....................................................................................................
|
LABOUR
|
No.
of each class
|
Rate
|
Approximate
quantity of work done
|
|
work
on which employed
|
Class
of labourers
|
| |
|
|
|
|
|
....................................
|
....................................
|
|
Signature of Subordinate-in-charge
|
Contractor's signature
|
|
Designation
..
|
Station
..
|
|
Station
..
|
Date
..
|
|
Date
..
|
|
Payment to Suppliers and Contractors
1313. Record of Measurements.-Payments for all work done otherwise than by
departmental labour and for all supplies are made on the basis of measurements recorded in Measurement
Books (Form E. 1313 given below) in accordance with the rules contained in this Chapter.
Form E 1313
Sheet 1)
COVER
......................................Railway
MEASUREMENT BOOK
No.................................
Engineering Department....................................... Division...............................................
Name ...................................................................
Designation...........................................................
Date of issue......................................................... Date of return......................................
___________________________________________________________________________________
(Title page)
Form E 1313
(Sheet 2)
MEASUREMENT BOOK
No.........................................................................
Division.................................................................
Issued to.....................................................................................................................................................
(Name & designation)
.............................................................................. on........................................................
(station)
(date)
Received by................................................................................................................................................
(Signature)
..............................................................................
............................................................
(Designation)
(Station)
............................................................
(date)
Date of first entry...................................................
Date of last entry...................................................
Date received in Division office after completion of book..................................................................
Certified that this Measurement Book contains pages numbering 1-100 (both pages inclusive)
which have been counted by me and are correct.
Signature.............................................
Designation.........................................
Date....................................................
INDEX
OF M.B.
(Sheet 4)
|
Sl.
Item No.
|
Particulars
of Entries running or final
|
Agreement
or work Order Ref.
|
Page
|
Remarks
|
|
From
|
TO
|
|
|
|
|
|
|
|
(Sheet 5)
|
Particulars
|
No.
|
L.
|
B.
|
D.
|
Contents
|
|
|
|
|
|
|
|
1314. The measurement books should be considered as very important record. All the
books belonging to a division should be numbered serially and a register of them (Form E. 1314 given
below) should be maintained in the divisional office showing (1) the serial number of each book, (2) the name
and designation of the person to whom issued, (3) the date of issue and (4) the date of its return, so that
its eventual return to the divisional office may be watched. A similar register (Form E. 1314 given
below) should also be maintained in the sub-divisional office. Books no longer in use should be withdrawn
promptly even though not completely written up. The eventual return of all measurement books should be
insisted on. They should be carefully preserved for ten years. To ensure this, measurement books should
be carefully listed and made over to the open line authorities when the construction divisions are closed.
Form No. E. 1314
............ RAILWAY
REGISTER OF MEASUREMENT
BOOKS
Department Division Station
|
Serial No. of the
measurement book
|
Date of Receipt
|
Name &
Designation of the person to whom issued
|
Date of issue
|
Name &
Designation of the person to whom transfer
|
Date of transfer
|
Date of return of
completed book
|
Remarks
|
|
|
|
|
|
|
|
|
|
1315. Recording of
Measurements-On the open line organisation of the Railways the
following powers can be exercised in recording measurements :--
(i) Inspectors of Works and Permanent Way Inspectors in Gr. II (Rs. 1600-2660) and Gr. I (Rs.
2000-3200) can record all measurement including ballast measurements subject to the test
checks given below, but cannot record earth work sectional measurements unless they are
specifically nominated by the Assistant Engineer on considerations of competency and
reliability. A 10% check by the Assistant Engineer is necessary for works costing upto
Rs. 25,000/-, if the value of the work exceeds the estimated cost by more than 10% and for
works costing above Rs. 25,000/- a 20% check by Assistant Engineer is necessary. In the
case of ballast and pitching stones measurements a 100% check on quality and the quantity
by the Assistant Engineer is necessary. The Check of the Assistant Engineer in respect of
earth work sectional measurements may be done at his discretion. Those Inspectors in
Gr. I (Rs. 2000-3200) may finalize measurement for work upto Rs. 10,000/- even when the
total value of the works exceeds the estimated value by more than 10%.
(ii) Inspector of Works and Permanent Way Inspectors in Grade III (Rs. 1400-2300) when they
hold independent charge, can record measurement for works costing upto Rs. 25,000/-
each, subject to a test check of 20% by the Assistant Engineer.
(iii) Sub-Overseers, Mistries having a diploma in Engineering and having more than three years
of service and those not having a diploma in Engineering but having six years experience to
be nominated by name by the Divisional Engineer can record measurements of works upto
Rs. 10,000/-, subject to a test check of 20% by the Inspector of Works.
(iv) Recording of Measurement of Elec. open line & construction Works.
(a) Shop Supdt./ Chief Traction Foreman, in grade Rs. 2375-3500; Sr. Elec. Foreman/ Elec.
Foreman/ Traction Foreman in Grade Rs. 2000-3200/- can record all measurements.
A 10% check by the Asstt. Elec. Engineer/Divisional/district Elec. Engg. is necessary for
the work costing upto Rs. 25,000/- each if the value of the work exceeds the estimated
cost by more than 10% and for works costing above Rs. 25,000/- and 20% check by Asstt.
Elec. engineer/Divisional/District Elec. engineer is necessary.
(b) Asstt. Elec.Foreman/Asstt. Traction Foreman/Sr. Elec.chargeman in grade Rs.1600-2660/-
can also record the measurements subject to 10% test check on the works costing upto
Rs. 25,000/- and 20% check on the works costing more than 25,000/- by Asstt. Elec.
Engg./ Divisional/District Elec. Engineer.
(c) Elec. Chargemen/Asstt. Elec. Foreman in Gr. Rs. 1400-2300 when they hold independent
charge can record measurements for works costing upto Rs. 25,000/- each subject to a test
check by 20% by the Asstt. Elec. Engg./Divisional/District Elec. engineer.
(d) Elec. Chargemen having a diploma in Elec. Engg. and having more than three years of
service and those not having a diploma in Elec. Engg. but having six years experience
nominated by name by the Divisional/District Elec. Engineer can record measurements of
works upto Rs. 10,000/- subject to a test check of 20% by the Asstt. Elec. Engineer/District
Elec. Engineer.
1316. On construction projects and special works, Sub-Overseer Mistries cannot
record measurements. Inspector of Works and Permanent Way inspectors cannot record measurements for
the supply of ballast, pitching stones and earth work. For all other works, Inspectors of Works and
Permanent Way Inspectors in Grade I & II can record measurements upto a value of Rupees One
lakh, subject to a
20 per cent test check by the Assistant Engineer. Measurement of ballast and pitching stones,
classification of ballast and measurement for earth work will be done by the Assistant Engineer.
1317. For measurement of earth work cross-sections levels may be recorded by Inspector of
Works in the field book which should be in ink or inked before test checking by the Assistant Engineer.
The Assistant Engineer should exercise a check of 100 per cent in the case of levels along the centre line
of alignment, and not less than 20 per cent of the remaining levels of the cross sections with the proviso
that this check should invariably be carried out in cross sections having cross slopes. All the corrections in
the field book must be initialed by the Assistant Engineer and no subsequent corrections should be made
by any person other than the Assistant Engineer who while doing so should record the reasons for the
same. The signature of the contractor or his authorised agent should be taken on every field book accepting
the correctness of levels recorded therein.
Plotting of the cross sections may be done on graph paper taking care that sufficiently
large scale is adopted for plotting and there is not much distortion of horizontal and vertical scales
adopted. After plotting the cross sections the levels should be inked and each sheet containing the cross
section should be signed by the Inspector of Works, Assistant Engineer and the contractor. While plotting
the cross sections, the proposed theoretical profiles of the earth work should also be plotted to ensure that
the work is done to actual requirements and to avoid future claims from the contractors. For computing
the quantity of earth work arithmetical calculation is to be preferred but if necessary counting of square
method can also be adopted.
1317-A: The field Books/Level Books used for recording the
levels should be machine numbered and these books should be maintained,
accounted and kept in safe custody in the same way as Measurement Books are
maintained, accounted and kept.
(Authority Boards letter No. 2007/ce.1/ct/8 dated
9-5-08)---ACS
NO.44
1318. In the case of bridge girders and steel fabricated structures the contractor can be
permitted to submit his bill based on completion drawings. These bills may be checked in the Drawing Office
and accepted for payment. No detailed measurements need be recorded in such case by the Assistant
Engineer in the measurement book.
1319. All measurement except as specified in paras 1317 and 1318 should be neatly taken
down on the measurement book issued for the purpose and nowhere else. For large works a
separate measurement book may be set apart, or if found convenient two or more books may be set apart
for different classes of works.
1320. Each set of measurements should commence with entries stating :-
(a) Full name of work as given in the estimate;
(b) Situation of work;
(c) Name of contractor;
(d) Number and date of agreement entered into with contractor or of work order issued in
his favour;
(e) Dates of commencement and completion of work; and
(f) Date of measurement;
(a) Name of supplier;
(b) Number and date of agreement with supplier or of the order for supply;
(c) Purpose of supply;
(d) Dates of commencement and completion of supply; and
(e) Date of measurement;
and should end with the dated initials of the person making the measurements. A suitable abstract
should then be prepared which should collect, in the case of measurements for work done the total quantities
of each distinct item of work relating to each sub-head of estimate.
1321. As all payments for work or supplies are based on the quantities recorded in the
measurement books, it is incumbent on the person taking the measurements to record the quantities clearly and
accurately. If the measurements are taken in connection with a running contract account on which work has
been previously measured, the reference to the last set of measurement should be recorded, and if the
entire job or contract has been completed, the fact should be recorded prominently and
initialed by
person taking the measurements. If the measurements taken are the first set of measurements on a
running account, of the first and final measurements, this fact should be suitably noted against the entries in
the measurement book.
1322. Instructions for the Maintenance of Measurement
Books.--The pages of the book should be machine-numbered and no page should on any account be torn out, nor should any entry be erased
or deffaced so as to be illegible. If mistake be made, it should be corrected by crossing out the
incorrect words or figures, and rewriting the correct words or figures, and the correction thus made should
be initialed. The entries must be made directly in the measurement books at the site of work. The copying
of entries from another rough note book or similar record is strictly forbidden. A reliable record is the object
to be aimed at, as it may have to be produced as evidence in a Court of Law.
1323. The entries in the measurement book should, if possible be made in ink, but when this is
not possible, the entries should be recorded with indelible or special copying pencil so as to render it
difficult to tamper with or to make unauthorised additions to or alterations in entries once made, the pencil
entries should not be inked over, but left untouched. The entries in the "contents or area" column should,
however, be invariably made in ink.
1324. Entries should be recorded continuously in the measurement book. No blank pages
should be left nor should any page be torn out, the cancellation being attested. When any measurements
are cancelled, the cancellation should be supported by the dated initials of the officer ordering the
cancellation, or by a reference to his orders initialed by the officer who made the measurement. In either case,
the reason for cancellation should be recorded.
1325. Each measurement book should be provided with an index which should be kept up to date.
1326. From the measurement book, all quantities should be clearly traceable into the
documents on which payment are made, and a reference to the voucher in which the quantities are entered
for payment, as well as the date of entry, should be given by an endorsement upon the original entries in
the measurement book, No contract certificate or bill should be signed without thus crossing off the
connected entry in the measurement book, and the document on which payment is made should invariably bear
a reference to the number and page of the book in which the detailed measurement are recorded.
1327. Standard
Measurements.-Detailed measurements may be dispensed with in the case
of periodical repairs when the quantities are recorded in efficiently maintained Standard measurement
books. In the case of letting out the work of whitewashing of quarters on contract the Railways can group
the quarters in Division or Sub-Division Area in such a way that each group includes quarters which
would individually entrail approximately the same equivalent surface area for whitewashing. The grouping
should broadly be such that all the quarters in one group should be susceptible of being given to one
contractor for the purpose of whitewashing. Non-standard bungalows of officers may, however, be excluded
from such grouping. The standard areas of white washing to be paid for in respect of one unit of quarters
in each group and approximate number of units to be whitewashed should be clearly shown in the
tender documents. Payments should be made for the number of quarters actually whitewashed on the basis
of such area per unit as indicated in the tender documents.
1328. Measurements based on Standard type
Drawings.-Detailed measurements are not required in the case of measurements of standard type staff quarters provided there is a suitable clause
in the agreement with the contractor to protect the railway legally and the Assistant Engineer certifies that
the work billed for has been carried out in accordance with standard type drawings then the quantities
as given in the schedule of Estimates for standard type quarters for the type concerned may be entered
in measurement books for all work above floor level without actual measurements being recorded.
For this purpose tenders for the construction of buildings for which type designs have been
prescribed should be invited at a rate per unit of complete building. The detailed specifications and measurement
of the type of building should be fully given out in tender papers. Bills for payment should be paid in terms
of the number of buildings put up multiplied by the rate approved per unit building. For regulating `on
account' payments a schedule of percentage payment due at various stage of construction of the building e.g. up
to sill level, up to ceiling level etc. should be included in the tender documents. Where items not covered
in the rate for the unit are required to be provided, they should be separately shown in the tender
documents clearly bringing out what would constitute these "extras" and how they would be measured and paid
for. Similar provision should also be made for any unforeseen items that may be required.
1329. This system may be extended with advantage to certain items of repair work almost
invariably done in complete units, such as colour washing and oiling, varnishing or painting of doors provided that
the Schedule of Estimates for standard type drawings gives the quantities for these items separately for
each room, the rooms being distinguished on the drawing and in the `estimate' by separate letters and also
to the painting of bridges, tank, tank staging and similar items which involves a very large number of
entries, if the work has been previously done and recorded in some extant measurement book. In the latter
case it should be sufficient to refer to the previous measurement and merely enter total quantities for
each bridge, tank, etc. provided that the Assistant Engineer is able to certify that the quantity of work done is
the same as that of the previous measurement which will have to be carefully filed under the Executive
Engineers signature.
1330. Measurements for Lump-Sum
Contract.-Detailed measurements are not required in
the case of a work done under a lump sum contract. Final payment in such cases may be made on
the certificate of the Assistant Engineer to the effect that the work has been completed according to
the drawings and specifications.
1331. Approximate
Measurements.-Detailed measurements may dispensed with in cases
in which payments `on account' for work actually executed are made on the certificate of a
responsible officer (not below the rank of Assistant Engineer) to the effect that not less than the quantity of work
paid for has actually been done and that the measurement are from plans or that they are
approximately estimated. The officer granting such certificate will be held personally responsible for any
overpayments which may occur on the work in consequence. Final payments should, however, in no case be
made without detailed measurements.
1332. Measurement of Ballast Train
Work.-It is not usually convenient to record in measurement books detailed measurement of work done by contractors in connection with the working
of ballast and material trains e. g. loading and unloading of ballast, permanent way and other
construction materials. In such cases ballast train or material train challans in the following form (E. 1332) should
be prepared in four copies by the subordinate supervising the loading of ballast or material. One copy
should be retained as office copy of the subordinate who trained out the material. Two copies should be sent
to the receiving subordinate through the guard of the ballast or material train. One copy should be
sent directly to the Assistant Engineer concerned immediately after loading to reach within 24 hours to
enable the Assistant Engineer to verify the `ballast or materials if required. The receiving subordinate
should check the quantites of materials received with those shown on the challan and accept it subject to
any remarks he may have to make. One copy of the accepted challan should then be submitted to the
Assistant Engineer concerned to enable the latter to prepare the contractor's loading and unloading bill. In this
case, the accepted challan takes the place of a measurement book.
Form No. E. 1332
......................RAILWAY
BALLAST/ MATERIAL TRAIN CHALLAN FORM
Department.............................................................Division.........................................................................
Ballast Train Report of .........................................train, ordered vide D.E. N's/A.E.N's No..........................
................................................working from Km. ..........................................Km. .......................................
on..........................................Engine No. ...............................Class.............................Composition of train
................................................Labour.....................................Mistries/Mates........................................Men
...............................................Women..................................Name of Contractor.........................................
|
Station
|
Time
|
Hours occupied
|
Trip No.
|
Work done
|
Trains crossed
|
Allocation
|
|
From
|
To
|
From
|
To
|
Name of work
|
Head account
|
|
|
|
|
|
|
|
|
|
|
|
|
Loaded
|
Unloaded
|
|
At
|
Trip No.
|
Contents
|
At
|
Trip No.
|
Contents
|
|
Km.
|
TP
|
Wagon
|
Description
|
Quantity
|
Km.
|
TP
|
Wagon
|
Description
|
Quantity
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contractor or his authorised Agent.
|
Inspector No
.
Section
|
B.T. Guard/Engg. Official
incharge
|
|
..20
|
|
20
..
|
|
A.E.N. No
.
|
D.E.N
.
|
|
|
Sub. Divn
|
Division
|
|
|
20
|
..20
..
|
|
Note:Ύ
On reverse
of this form, the class, capacity and number of each wagon should be
shown. Also, particular of detentions to trains other than for Engineering
work.
1333. The Measurement of Ballast.--Ballast should as a rule, be measured in stacks.
When ballast taken over by the Railway is trained out, the correctness of the measurements recorded in
the ballast train challans, after making due allowance for shrinkage enroute should be checked with the
original stack measurements. In cases where owing to uneven surface of the stacking ground or for want of
space in the quarry, etc. ballast cannot be stocked in stacks of convenient sizes and where in
consequence ballast has to be measured and taken directly in wagons, the procedure laid down in para 1332 may
be adopted subject to a test check of 20% of the wagon measurements by the Assistant Engineer.
1334. The Divisional or Executive Officer should make it a point to see that the
measurement books are maintained in accordance with the rules laid down in paragraphs 1313 to 1332 ante and that
the measurements recorded are complete records of each kind of work done for which certificates have
been given.
1335. Subject to provisions of paragraph 1312 and 1327 to 1332 ante, the bills of contractors
for work done or supplies made should be prepared in any one of the following forms according to
that circumstances mentioned below against each :-
-
(i) Petty Contract bill, Form E. 1336.
-
(ii) Running or On Account bill, Form E. 1337.
-
(iii) Final Bill, Form E. 1338. and
-
(iv) Hand Receipt, Form E. 1339.
The final bill Form (E. 1338) should specifically provide that the contractor concerned accepts
the amount billed for as a final payment in settlement of all his claims in respect of the particular work. Bill
for work done should necessarily be prepared in any one of the above forms. Bills of supplies submitted
on supplier's own forms may, however, be accepted when prepared in English or Hindi, any further
particulars required by the departmental form being added by the disbursing officer. All bills passed against a
work order should be noted on the work order.
1336. The petty bill form (Form E. 1336) should be used for making payments to contractors
in connection with works or supplies when a single payment is made for a job or contract on its completion.
It may also be used in paying several contractors employed on parts of one large work or several works
on one section of the line.
From
E 1336 (Continued to........ List of forms)
1337.
The Running or Account bill from
(Form E.1337 below ) is indicated for use in contract works only and not
supplies. On account payments before the completion of a work should
be made through this form.
Form E. 1337
..........................
RAILWAY
ENGINEERING
DEPARTMENT
ON
ACCOUNT' CONTRACT CERTIFICATE
No.
.
Division
.
Name & Address of Contractor
.
Name of work
.
Authority for work
Agreement No
I.
Account of work executed
|
On
account payment
for
work covered by
approximate
or plan measurement
|
Item
of work
|
Unit
|
Rate
|
Quantity
executed since last certificate
|
Quantity
executed upto date as per measurement
|
Payment
on the basis of actual measurement
|
Remarks
(with reasons for delay in recording measurement shown in column
(1)
|
|
Total
as per last certificate
|
Since
last certificate
|
Total
Upto date
|
Upto
date
|
Since
last certificate
|
|
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
|
Rs.
|
Rs.
|
Rs.
|
|
|
|
|
|
Rs.
|
Rs.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Whenever there is any entry in column 10 on
the basis of actual measurements the whole of the amount previously paid
without detailed measurement should be adjusted by a minus entry in column
2 equivalent to the amount shown in column 1, so that the total up to date
in column 3 may become nil.
When there are two or more entries in
column 10 relating to each sub-head of estimate they should in the case of
works the accounts of which are kept by Sub-heads, be totalled and the
total recorded in column 11 for posting the Register of Works.
|
|
|
|
(B)
|
Total value of work done to date
(A) Deduct value of work shown on last Certificate Net value of
work since last Certificate (F) Figure (F) in words.
|
|
|
|
II.
Certificate and Signature
1.
The measurements on which are based the entries in columns 4 to 10
of Account I were made by
. On
and are recorded at pages
. of measurement book, No.
.
2.
Certified that in addition to and quite apart from the quantities
of work actually executed as shown in column 8 of Account I. some work has
actually been done in connection with several items and the value of such
work is in no case, less than the on account payments as per column 3 of
Account 1, made or proposed to be made for the convenience of the
Contractor in anticipation of and subject to the results of detailed
measurement which will be made as soon as possible.
3.
Certified that no materials the cost of which has not been
recovered, were issued to the contractor.
..
.............Rank-incharge of work
Signature of Contractor
Signature of Officer
Preparing the Bill
Dated
Dated
.
................................
..
Witness of Signature to Contractors
Designation
___________________________________________________________________________________
III.
Memorandum of Payments
1. Total value of work actually measured as per Account I, Column 9, entry
(A)
2. Total up-to-date on account payments for works covered by approximate or
Plan measurement as per Account I, Column 3, entry (B)...............................
3. Total (1 and 2)....................................................................................................
4. Deduct amount withheld on account of security deposits :--
(a) From previous bill as per last certificate
(*k)
(b) From this certificate
5. Balance i. e. up-to-date payments..................................................Item (3-4)
6. Total amounts of payments already made as per entry (k) of last certificate
No...............................dated.......................................20..............forwarded
to the Accounts Officer on ...........................................................................
7. Payments now to be made :
(a) For stores supplied ... ... ... ... ...
...
**
(b) By Cash or Cheque ... ... ... ... ... ...
___________________________________________________________________________________
IV. Here enter the nature of check measurements taken or other examination of work and
the results of such examination.
Certified for payment of Rs...........................chargeable to.........................and to be including
in accounts for...........................20..............
To be paid in cash / by cheque in presence of............................
...........................................................
..........................................................................
Head Clerk or Accountant Executive
Engineer.......................................Division
V. Received Rs. **
in cash...................... as per above memorandum on account of this work
Dated.......................................20............
Value of stock supplied.....................
Stamp
Witness (1) ...................................
Total as above.................................
(2) ..................................
Signature of Contractor...................
___________________________________________________________________________________
VI. Entries to be made in Accounts Office
Accounts Bill No..........................dated.............20.....
Entered in Abstract No................dated.............20.....
Passed for Rs...............................(..........................)
Amount passed.........................................................
Less deduction Rs....................................................
Net amount payable.................................................
Rupees.....................................................................
Chargeable to..........................................................}
} Posted by.........checked by...........
Passed by...............................................................
}
.......................................
Accounts Officer
VII. Entries to be made by Pay Department
Cash entry dated..........................20........
Amount paid Rs........................................
Amount unpaid Rs...................................
Total unpaid Rs........................................
Paid in presence...................................... ..................................
........................
Head Pay Clerk
_____________________________________________________________________________________________________
* This figure should be tested to see that it agrees with the total of item 6 & 7.
** If the net amount to be paid is less than Rs. 10 and it cannot be included in a
cheque, payment
should be made in cash, this entry being altered suitably and the alteration attested by dated
initials.
* Here specify the net amount payable vide item 7 (b).
The payees acknowledgement should be for the gross amount paid as per item 7(i. e., A &B).
** Payment should be attested by some known person when the payee's acknowledgement is
given by remarks seal or thumb impression.
1338. The final Bill from (From E 1338) should be used for making final payments, i. e.
on closing running accounts for works. Normally only one final bill should be prepared against an
agreement or work order. But in cases where groups of annual repair works are included in one agreement or
work order, there is no objection to more than one final bill being prepared on the completion of each group
or certain groups.
From E. 1338
Railway
ENGINEERING
DEPARTMENT
FINAL
CONTRACT CERTIFICATE
No.
. Name
& Address of Contractor
.
Name of work
Division
.
Authority for work
Agreement No
I.
Account of work executed
|
On
account payment
for
work covered by
approximate
or plan measurement
|
Item
of work
|
Unit
(in words and figures)
|
Rate
(in words and figures)
|
Quantity
executed since last certificate
|
Quantity
executed upto date as per measurement
|
Payment
on the basis of actual
measurement
|
Remarks
(with reasons for delay in recording measurement shown in column
(1)
|
|
Total
as per last certifi-cate
|
Since
last certificate
|
Total
Upto date
|
Upto
date
|
Since
last certificate
|
|
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
|
Rs.
|
Rs.
|
Rs.
|
|
|
|
|
|
Rs.
|
Rs.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Whenever there is an entry in column 10 on
the basis of actual measurement, the whole of the amount it previously
paid without detailed measurement should be adjusted by a minus entry in
column 2 equivalent to the amount shown in column 1, so that the total up
to date in column 3 may become nil.
When there are more entries column 10
relating to each sub head of estimate, they should, in the case of works,
the accounts of which are kept by sub-heads, be totalled and the total
recorded in column 11 for posting the Register of works.
|
|
|
|
(B)
|
Total value of work done to date
(A). Deduct value of work shown on last certificate. Net value of
work since last certificate (F) Figure (F) in words.
|
|
|
|
II.
Certificate and Signature
1.
The measurements on which are based the entries in column 4 to 10
of Account I were made by
.. Overseer on
..
No and are recorded at pages
of, Measurement Book
No.
.
2.
Certified that no materials, the cost of which has not been
recovered, were issued to the Contractor.
Rank
Incharge of Work
.
Dated
Signature of Date Signature of Officer
Designation
Contractor
preparing the bill
I have no other claim outstanding against
. Railway for
work done or for labour or materials supplied or on any other account and
the payment of this bill shall be in final settlement of all my claims in
respect of the work to which Agreement/Work Order No.............. dated
....................20 with the Railway relates.
..
.
.
Witness
of Signature
Signature of
Officer
Signature of the Contractor
Full
Address
Dated
...
III.
Memorandum of payments
|
1.
Total value of work actually measured as per Account 1,
column 9, entry (A)
2.
Total amount of payments already made as per entry (k) of
last certificate No
. dated
..19
.forwarded to the Accounts Officer on
3.
Payments now to be made-
(a)
For Stores supplied
(b)
By Cash
.
(c)
Cheque
..
|
Rs.
|
P.
|
IV.
Here enter the nature of check measurements taken or other
examination of work and the results of such examination.
Certified
for payment of Rs @ @
. chargeable to
and to be
included in accounts for
.. 20
.
To
be paid in cash/by cheque in presence of
Head
Clerk or Accountant
Executive Engineer
Division
V. Received
Rs.*
as final payment in settlement of demand as per details
above on account of this
work
..
..............................
STAMP
@@Signature and designation
of
Signature of Contractor
witnessing Officer
Date
Date
..
____________________________________________________________________________________
VI.
Entries to be made 'm Accounts Office (on open line)
Accounts Bill No
dated
.
Entered in abstract No
.
dated
Passed for Rs. .........................(
.)
..
Amount passed Rs
................
Net Amount payable
.......
Less deduction Rs
..
Rupees
Chargeable to
.Posted by
Passed by
Checked by
.
.
Accounts
Officer
VII.
Entries to he made by Pay Department (on open lines)
Cash entry
dated
.
Amount paid Rs
..
Amount unpaid Rs
..
..
Total Rs
..
.
Paid in my presence.
..
.................................
Head Pay Clerk
________________________________________________________________________________________
@
If the net amount to be paid is less than Rs. 10 and it cannot
be included in a cheque, the payments should be made in cash, this entry
being altered suitably and the alteration attested by dated initial.
@@ Here specify the net amount payable, vide
item 3 (b and c).
*
The payee's acknowledgement should be for the gross amount paid as
per item 3 (i.e., a and b-c).
@
Payment should be attested by some known person when the
payee's acknowledgement is given by mark, seal or thumb impression.
1339. The Hand Receipt (Form E. 1339) is intended to be used for all miscellaneous payment
and advanced for which Forms E. 1336 to E. 1338 are not suitable.
Form E. 1339
HAND RECEIPT FORM
|
|
(To be used indifferently for payments for works materials or
other services.)
|
|
Payee
..
|
No.
.. Division
|
|
Name of work
..
|
Dated
|
|
Date of present payment
.
|
Received from the Executive Engineer in charge
of
..
|
|
Value of work or supplies to date of latest measurements Rs
|
Division the sum of Rs
.
Name of work or purpose for which payment is made-
|
|
Payments previously made
...Rs.
|
Paid by cash@
|
|
Payments now made
...Rs.
|
Paid by cheque@
..
|
|
Distribution of payments and quantity by sub- heads or other
necessary particulars :-
|
Paid by me*
.
|
|
|
Paid in my presence*
|
|
Rs.
P.
|
|
|
Initials of officer making the payments
|
Witnesses
|
: Signature
: Stamp
|
|
....................................
|
|
|
Executive Engineer
|
Designation
|
If the person receiving
money signs in the vernacular, he should also enter in the vernacular the
amount received and his place of residence, his name being noted in
English on the voucher. If unable to write, his mark or seal to the above
entries should be attested by two competent witnesses, in whose presence
the nature of the payment should be fully explained.
______________________________________________________________________________________________
@The officer or
subordinate authorising payment will initial the remark applicable to the
case.
*The person actually
making the payment or in whose presence the payment is made, should
initial, the mark applicable
1340. Preparation of Contractors Bills.-No fees should be charged either for forms of bills
supplied or for clerical assistance rendered in the preparation of bills. A contractor requiring a copy of his
contract certificate or an extract from his account in the contractor's ledger (see paragraph 1483) should be
furnished with the same at a charge of Rs. 10/- which should be credited to Government as a miscellaneous
receipt under the head "Receipts on Capital Account-Miscellaneous Receipts". In the case of works charged
to ordinary Revenue such receipts may be booked to Z-650.
No request from the contractor for supply of a copy of contract certificate or an extract from
his account in the ledger beyond a period of six years from the date of closing of contract should be entertained
1341. In all contractors' work and store bills the units calculation and rates should be entered
in words as well as figures. Whenever fraction of rupee occur in the totals of contractors' bills fractions
less than half may be disregarded and half a rupee and over may be taken as rupee, before forwarding
a contractor's bill to the Accounts Officer for payment the Executive Engineer should satisfy himself as
to the correctness of the quantities billed, for the rates and all recoveries.
1342. Other Miscellaneous
Payment.--Other payments which an Executive Engineer has
to arrange are with regard to pay, allowances and other miscellaneous personal claims of the
constructions staff such as advances of pay, travelling allowances, withdrawals from
P.F. etc. Such claims should
be dealt with in accordance with the rules and orders in the relevant sections of the Indian Railway Codes.
1343. Bill for Stores
purchased.--This bill will be prepared in Form S. 2817 which will be
printed in English, Hindi and the vernacular of the district in which used. Vendors of stores should be encouraged
to use these forms which may be supplied free of charge. In the case of final payment on a running contract
for the supply of stores, the same form, but printed on yellow coloured paper, will be used, and
disbursement made as on final contract certificates. The procedure laid down in paragraph 739 of the Indian Railway
Code for the Stores Department should be followed in passing claims for stores supplied.
1344. Pay Order.--This Form (E. 1344) is to be used only in the case of such
miscellaneous payments as refund of earnest money, payment of court attachments., & Pay orders will be bound
in books and will be machine-numbered. These books will be issued on requisition only to those officers
who have been authorised by the General Manager to use them.
Form No. E. 1344
PAY ORDER
|
Book No
..Serial
No
|
Book No
..Serial
No
|
|
Case
No
Dated
|
Case
No
Dated
|
|
(Counterfoil)
|
|
|
TO
..
.
|
TO
..
.
|
|
Pay
to
.
|
Pay
to
.
|
|
Rupees (in
words)
|
Rupees (in
words)
|
|
on account
of
.
|
on account
of
.
|
|
chargeable to
..in
|
chargeable to
..in
|
|
account
for
20
..
|
account
for
20
..
|
|
Rs
.
|
Rs
.Signature
.
|
|
account
for
.20
..
|
Designation
|
|
Rs
.............
|
Received the sum of Rupees
.as
above in full settlement of all demands.
|
|
......................................
initials of the Officer signing the
pay order.
|
Signature of payee
.
|
|
|
Date of payment
.
|
|
Designation
..
|
Witness
|
1345. General Rules.-Should any of the prescribed forms not be used, care should be taken
to see that no particulars, certificate or signature required by the prescribed forms are omitted. The
general rules laid down in the following paragraphs should be observed in connection with the claims referred
to herein as "bills".
1346.
Executive Engineers submitting bill for payment should satisfy themselves that the
same are correct and complete in every particular and that sufficient authority exists for their payment.
1347.
All bills be signed by the officer responsible for the outlay in token of his acceptance of
the claims, any alterations or corrections therein being duly initialed. In the case of contractors' bill the
signature of the contractor are also required in token of their acceptance of the correctness of the bill submitted.
1348.
A programme should be drawn up by the Accounts Office fixing the dates for the
submission to it for check and payment of pay and allowance bill, muster sheets or labour pay sheets and other
claims of a recurring nature. In the submission of bills executive officers should, except in emergent
cases, adhere strictly to the dates laid down in the programme in order to ensure punctual payment.
1349.
Bill should be dated and correctly allocated to the heads of accounts classification
and sub- heads of works concerned. In the case of bills chargeable to works, for which estimates are
sanctioned (see paragraph 701) the allocation should be given in full detail as on the sanction estimates. This
rule applies to all vouchers, whether cash or adjustment and whether of open lines or of lines under construction.
1350. In the case of bill pertaining to Revenue working expenses, the month to which the bill
is debitable should be noted, as owing to the use of the head "Demands Payable" it is, as a general
rule practicable to adjust the liability against the final head of account in the accounts of that month, even if
the payment may be made in the following month.
1351. No receipts from the parties to whom the bill is payable should normally be taken
in anticipation of payment. The receipt of the payee should ordinarily be taken upon the original passed
bills or pay order. But when two or more bills or pay orders are paid by a
cheque, a receipt for the
cheque should be treated as a joint acknowledgement of payment of all the bills or pay orders, as the case may
be. The receipt should, however, give full particulars of all the bills or pay orders in discharge of which
the payment is made.
1352. No claims of any class or description other than pay and other personal claims of
employees may be drawn in bills in the name of any servant of the railway.
1353.
To facilitate payments, the name of Pay District, the place of payment and the name
and designation of Witnessing Officers (if necessary) should be noted on all bills and in the case of
labourers, the name of the father of each payee in addition to his own name should be entered in Labour Pay Sheets.
Check of Initial Records
1354. All initial records, whether of lines under construction or of open line should, before
they are presented for payment, be checked to see--
-
(a) That they have been prepared in the prescribed forms and that they are arithmetically correct;
-
(b) that the expenditure recorded has received the sanction either special or general, of the authority
competent to sanction it ;
-
(c) that the expenditure recorded has been incurred by an officer competent to incur it ;
-
(d) that the expenditure does not involve a breach of any of the canons of financial propriety.
-
(e) that the expenditure recorded is covered by provision in the sanctioned budget allotment; and
-
(f)
that the charge is correctly classified, and if a charge is debitable to the personal account of
contractor, employee or other individual or is recoverable from him under any rule or order, it
is so recorded on the initial record and in prescribed account (where such account is kept by
the Executive Engineer).
1355. The following subsidiary points require attention in the check of
(i) muster sheets and
labour pay sheets and (ii) Contractors bills :-
(i) Muster Sheets and Labour Pay Sheets.--- It should be seen---
-
(a) that no classes of establishment not properly chargeable to works vide paragraph 1121
have been included therein;
-
(b) that the wages of employees are charged at the rates sanctioned by the competent authority;
-
(c) that the wages charged for each gang or a group of labour under each subordinate in
the case of maintenance works do not without sufficient reason (which should be
investigated and recorded) vary materially form month to month; and
-
(d) that the number, rates, period of employment and total amount are within the sanction.
(ii) Contractor's Bills.---It should be seen--
-
(a) that there are no delays in making measurements or in preparing bills after the
measurements have been taken;
-
(b) that rates higher than those provided in the agreement or work order are not allowed
without the specific sanction of the competent authority;
-
(c) that the running account and final bills are checked with the postings in the contractor's
ledger, form E. 1483;
-
(d)
that recoveries have been correctly made according to rules on account of materials
issued against items of works for which labour and material rates are paid;
-
(e)
that for items for which labour, rates only are paid the quantities of materials issued and
charged finally to works are not excessive ( the cost of materials wasted in defective
works subsequently rectified should be recovered);
-
(f)
that the quantities executed are according to the sanctioned plans and estimates; and
-
(g)
that the methods of measurement are correct.
Technical checks detailed as items (e) to (g) above should, as a rule be exercised in the
Drawing Office under the supervision of the Executive Engineer.
****** |